Which of the following statements is NOT true?
A) The volume variance for fixed cost will always be zero.
B) The flexible budget variance is the comparison of actual results to the flexible budget.
C) The flexible budget variance for fixed costs will always be zero.
D) When a flexible budget is used in a performance report, it is prepared for the actual level of units sold.
Correct Answer:
Verified
Q171: The master budget variance is the difference
Q172: With regard to a static budget instead
Q173: The flexible budget total cost formula applies
Q174: Which of the following causes the master
Q175: Both the static budget and the flexible
Q177: With regard to flexible budgets, which of
Q178: Another name for a static budget is
Q179: A flexible budget is a budget prepared
Q180: The volume variance is the difference between
Q181: Everyone Deserves to Smile mobile dentist office
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents