16-113 the Maximum Cost Savings That Can Be Generated with This

Question 102

Multiple Choice

16-113 The maximum cost savings that can be generated with this new equipment has been estimated to be $264,237.In order to accept this project,what is the minimum number of years the projected savings must be realized before the project breaks even?


A) 3.7 years.
B) 4.7 years.
C) 5.7 years.
D) 6.7 years.
E) 7.7 years.

Correct Answer: