Johann Builders has a fixed -price contract providing $120,000 of revenue.Construction on the contract was begun in 2013 and was completed in 2014.Information relating to the contract is as follows:
What amount of income should Johann recognize in 2014 assuming that the company appropriately uses the percentage-of-completion method of income recognition?
A) $9,286
B) $15,000
C) $17,000
D) $7,000
Correct Answer:
Verified
Q21: A company uses the percentage-of-completion method to
Q33: Goods on consignment should be included in
Q36: Golden Construction Company uses the percentage-of-completion method
Q37: On May 1,2014,Lavender Construction Company entered into
Q39: Samuels Company began operations on January 1,2014,and
Q43: Warthog Enterprises,which began operations on January 1,appropriately
Q45: Hussong,Inc. ,appropriately uses the installment sales method
Q46: When a contractor determines that a contract
Q48: The completed-contract method (as opposed to the
Q53: When Progress Billings are made by a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents