Beaver Company Used a Predetermined Overhead Rate Last Year of $2

Question 29

Multiple Choice

Beaver Company used a predetermined overhead rate last year of $2 per direct labour hour based on an estimate of 25,000 direct labour hours to be worked during the year.Actual costs and activity during the year were:
 Actual manufacturing overhead cost  incurred $47,000 Actual direct labour hours worked 24,000\begin{array}{|l|l|}\hline \begin{array}{l}\text { Actual manufacturing overhead cost } \\\text { incurred }\end{array} & \$ 47,000 \\\hline \text { Actual direct labour hours worked } & 24,000 \\\hline\end{array}
What was the under- or overapplied overhead last year?


A) $1,000 underapplied.
B) $1,000 overapplied.
C) $2,000 underapplied.
D) $3,000 overapplied.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents