The Porter Company has a standard cost system.In July,the company purchased and used 22,500 kilograms of direct material at an actual cost of $53,000,the materials quantity variance was $1,875 unfavourable,and the standard quantity of materials allowed for July production was 21,750 kilograms.What was the materials price variance for July?
A) $2,725 favourable.
B) $2,725 unfavourable.
C) $3,250 favourable.
D) $3,250 unfavourable.
Correct Answer:
Verified
Q3: Tower Company planned to produce 3,000 units
Q4: Which department is usually held responsible for
Q5: Drake Company purchased materials on account.The
Q6: Cox Company's direct material costs for
Q7: What does a favourable labour rate variance
Q9: To measure controllable production inefficiencies,which of the
Q10: What do the terms "standard quantity allowed"
Q11: A labour efficiency variance resulting from the
Q12: If a company follows a practice of
Q13: What does an unfavourable labour efficiency variance
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents