Which of the following is the final activity in the systems development life cycle?
A) monitoring of the system
B) ongoing maintenance activities
C) preparation of the post-implementation review report
D) user acceptance of the post-implementation review report
Correct Answer:
Verified
Q85: Which of the following is not generally
Q86: An analyst who asks the question,"Does the
Q87: Which factor is not investigated during the
Q88: Ideally,employees should receive training on a new
Q91: Which of the following control design considerations
Q97: Changing tax rates in a software program
Q102: Performing revisions to existing program code is
Q103: Describe the post-implementation review activity.
Q104: Over the entire life of a typical
Q105: Post implementation review is conducted to
A)determine whether
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents