Waycross Construction Company Has a Pipeyard Operation Which Is Run

Question 74

Multiple Choice

Waycross Construction Company has a pipeyard operation which is run as a cost center. They are preparing a performance report for the month of March and have provided the data below:
 Cost Center  Flexible  Flexible Budget  Performance Report  Actual  Budget  Variance  U/F % variance  U/F  Wages & benefits $81,200$80,000 Office lease expense 42,06045,000 Depreciation expense 39,60042,000 Insurance expense 33,49030,000 Other expense 7,1208,000$203,470$205,000\begin{array}{|l|r|r|r|r|r|r|}\hline \text { Cost Center } & & \text { Flexible } & \text { Flexible Budget } \\\hline \text { Performance Report } & \text { Actual } & \text { Budget } & \text { Variance } & \text { U/F } & \% \text { variance } & \text { U/F } \\\hline \text { Wages \& benefits } & \$ 81,200 & \$ 80,000 \\\hline \text { Office lease expense } & 42,060 & 45,000 \\\hline \text { Depreciation expense } & 39,600 & 42,000 \\\hline \text { Insurance expense } & 33,490 & 30,000 \\\hline \text { Other expense } & 7,120 & 8,000 \\\hline & \$ 203,470 & \$ 205,000 \\\hline\end{array}
-
How much is the percentage variance for Wages and benefits?


A) 2.2 % F
B) 2.2 % U
C) 1.5% F
D) 1.5% U

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents