Which of the following statements is incorrect with respect to revenue recognition of construction contracts?
A) The percentage-of-completion method is to be applied for fixed price contracts if the recognition criteria are satisfied.
B) AASB 111 requires individual construction contracts to be accounted for separately and the requirements of the standard to be applied separately to each contract.
C) The percentage-of-completion method should be used, provided certain conditions are met that enable the outcome of the contract to be reliably estimated.
D) Percentage-of-completion method requires contract revenue to be matched with progress billings, resulting in the reporting of revenue, expenses and profit which can be attributed to the amount billed to customers.
E) E: All of the given answers.
Correct Answer:
Verified
Q54: Which of the following is not an
Q55: Hillier Construction Ltd commenced the construction of
Q56: Using the cost method to calculate the
Q57: The following journal entries were recorded by
Q58: According to AASB 111 a group of
Q59: Which of the following is not a
Q60: The percentage of completion can be measured
Q62: Lonsdale Ltd sells mobile phones and provides
Q63: Werribee Direct Ltd is a mail order
Q64: Bellarine Ltd is publisher of Mode magazine
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents