Harald, Inc -Refer to the Figure What Is the Budget Variance for Setups in an Activity-Based

Question 103

Multiple Choice

Harald, Inc., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed:
 Activit  Cost Formula  Maintenance $11,000+$0.11 per machine hour  Machining $25,000+$0.50 per machine hour  Setups $50 per batch  Purchasing $200+$45 per purchase order \begin{array} { l l } \text { Activit } & \text { Cost Formula } \\\hline \text { Maintenance } & \$ 11,000 + \$ 0.11 \text { per machine hour } \\\text { Machining } & \$ 25,000 + \$ 0.50 \text { per machine hour } \\\text { Setups } & \$ 50 \text { per batch } \\\text { Purchasing } & \$ 200 + \$ 45 \text { per purchase order }\end{array}
-Refer to the figure.Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders  Maintenance $11,500 Machining 28,300 Setups 550 Purchasing 1,000\begin{array} { l r } \text { Maintenance } & \$ 11,500 \\\text { Machining } & 28,300 \\\text { Setups } & 550 \\\text { Purchasing } & 1,000\end{array} What is the budget variance for setups in an activity-based performance report?


A) $50 F
B) $50 U
C) $800 U
D) 1,000 F

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents