Jones Manufacturing Has Used Activity Based Costing to Assign Costs

Question 124

Multiple Choice

Jones manufacturing has used activity based costing to assign costs to Models X and Y as given in the table below:
 ModelX  ModelY  Units produced 24,00030,000 Machine hours 7,5008,500 Direct labour hours 8,00012,000 Material handling (number of moves)  4,0006,000 Setups 5,0007,000 Purchase orders 3040 nspections 10,00014,000 Product line variatinns. 812\begin{array}{lrr}& \text { ModelX } & \text { ModelY } \\\text { Units produced } & 24,000 & 30,000 \\\text { Machine hours } & 7,500 & 8,500 \\\text { Direct labour hours } & 8,000 & 12,000 \\\text { Material handling (number of moves) } & 4,000 & 6,000 \\\text { Setups } & 5,000 & 7,000 \\\text { Purchase orders } & 30 & 40 \\\text { nspections } & 10,000 & 14,000 \\\text { Product line variatinns. } & 8 & 12\end{array}
The following overhead costs are reported for the following activities of the production process:
 Material handling $40,000 Labour-related overhead 120,000 Setups 60,000 Product design 100,000 Batch inspections 120,000 Central purchasing 70,000\begin{array}{lr}\text { Material handling } & \$ 40,000 \\\text { Labour-related overhead } & 120,000 \\\text { Setups } & 60,000 \\\text { Product design } & 100,000 \\\text { Batch inspections } & 120,000 \\\text { Central purchasing } & 70,000\end{array} Jones manufacturing has used activity based costing to assign costs to Models X and Y as given in the table below:
 Activity  Cost  Pool  Model  Model X  Model  Model Y  Pool  Driver  Rate  X  Cost  Y  Cost  Total  Activity  Activity  Material  handling $40,00010,000$44,000$16,0006,000$24,000$40,000 Labour-  related  overhead $120,00020,000$68,000$48,00012,000$72,000$120,000 Setups $60,00012,000$55,000$25,0007,000$35,000$60,000 Product  design $100,00020$5,0008$40,00012$60,000$100,000 Batch  inspections $120,00024,000$510,000$50,00014,000$70,000$120,000 Central  purchasing $70,00070$1,00030$30,00040$40,000$70,000 Total $209,000$301,000$510,000\begin{array}{|l|r|r|r|r|r|r|r|r|}\hline\text { Activity } & \text { Cost } & & \text { Pool } & \text { Model } & \text { Model X } & \text { Model } & \text { Model Y } \\&\text { Pool } & \text { Driver } & \text { Rate } & \text { X }& \text { Cost } & \text { Y } & \text { Cost } & \text { Total } \\&&&&\text { Activity } & & \text { Activity } & &\\\hline \begin{array}{l}\text { Material } \\\text { handling }\end{array} & \$ 40,000 & 10,000 & \$ 4 & 4,000 & \$ 16,000 & 6,000 & \$ 24,000 & \$ 40,000 \\\hline \begin{array}{l}\text { Labour- } \\\text { related } \\\text { overhead }\end{array} & \$ 120,000 & 20,000 & \$ 6 & 8,000 & \$ 48,000 & 12,000 & \$ 72,000 & \$ 120,000 \\\hline \text { Setups } & \$ 60,000 & 12,000 & \$ 5 & 5,000 & \$ 25,000 & 7,000 & \$ 35,000 & \$ 60,000 \\\hline \begin{array}{l}\text { Product } \\\text { design }\end{array} & \$ 100,000 & 20 & \$ 5,000 & 8 & \$ 40,000 & 12 & \$ 60,000 & \$ 100,000 \\\hline \begin{array}{l}\text { Batch } \\\text { inspections }\end{array} & \$ 120,000 & 24,000 & \$ 5 & 10,000 & \$ 50,000 & 14,000 & \$ 70,000 & \$ 120,000 \\\hline \begin{array}{l}\text { Central } \\\text { purchasing }\end{array} & \$ 70,000 & 70 & \$ 1,000 & 30 & \$ 30,000 & 40 & \$ 40,000 & \$ 70,000 \\\hline \text { Total } & & & & & \$ 209,000 & & \$ 301,000 & \$ 510,000\\\hline\end{array} Jones Manufacturing wants to implement an approximately relevant ABC system by using the two most expensive activities for cost assignment.
-Refer to the figure.Under this new approach,what is the new pool rate for batch inspection costs?


A) $0
B) $5
C) $10.625
D) $15.525

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents