Which of the following descriptions regarding critical path analysis/PERT charts is true?


A) The first step in preparing a PERT chart is assigning time estimates to each activity.
B) The illustration of the relationship comes before the calculation of earliest start time and latest finish time.
C) The identification of any slack comes before the calculation of earliest start time and latest finish time.
D) Assigning time estimates to each activity comes after the identification of any slack.