Solved

Which of the Following Regarding Project Times Is Not True

Question 49

Multiple Choice

Which of the following regarding project times is not true?


A) The latest start time is the latest possible time at which a task can commence without delaying the project.
B) The latest start time is used in calculating the amount of slack or spare time available for disruptions.
C) Activities on the critical path can have slack time built into them.
D) The difference between the earliest finish time and the latest finish time is the amount of slack that is available.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents