Nichols Construction Company (NCC)entered into a Contract to Build a Shopping

Question 76

Multiple Choice

Nichols Construction Company (NCC) entered into a contract to build a shopping complex for $1,900,000.Construction commenced on July 1,2017,with a planned completion date of December 31,2019.A summary of the related accounting information is provided below:
Nichols Construction Company (NCC) entered into a contract to build a shopping complex for $1,900,000.Construction commenced on July 1,2017,with a planned completion date of December 31,2019.A summary of the related accounting information is provided below:   How much would the balance in accounts receivable be on the balance sheet of NCC at the end of 2019 if NCC uses the percentage of completion method? A) $0 B) $250,000 C) $290,000 D) $800,000
How much would the balance in accounts receivable be on the balance sheet of NCC at the end of 2019 if NCC uses the percentage of completion method?


A) $0
B) $250,000
C) $290,000
D) $800,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents