Lagory Co.started a contract in June 2017 to build a bridge at a fixed price of $14 million.The bridge was to be completed by October 2019.Total cumulative costs incurred by the end of December 2017 and 2018 were $2 million and $6 million,respectively.Lagory Co.is unable to estimate the total costs of the project prior to completion.Final costs at the end of the project totalled $11 million.How much revenue will Lagory Co.report in 2018?
A) $2,000,000
B) $3,000,000
C) $4,000,000
D) $14,000,000
Correct Answer:
Verified
Q55: Soorya Manufacturing makes educational toys that are
Q62: Queensbridge Corp.started a contract in June 2017
Q63: Ying Construction Company entered into a contract
Q64: Yang Construction Company entered into a contract
Q65: Nichols Construction Company (NCC)entered into a contract
Q66: Early in 2018,Forest Ltd.signed a contract to
Q68: WestCoast Co.started a contract in June 2017
Q69: Jones Contractors Inc.agreed to construct a building
Q70: Pool Contractors (PC)entered into a contract to
Q71: Algae builds large ships and uses the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents