Task X is expected to take 3 days to complete.The maximum (latest) earliest finish date for any predecessors to task X is 10.Therefore, the earliest finish for task X is:
A) 7
B) 10
C) 13
D) Cannot determine from the information given
Correct Answer:
Verified
Q22: Why do businesses often NOT pursue the
Q23: Project manager Bill Jones has determined that
Q24: Which of the following is a project?
A)The
Q25: Where in a project schedule is a
Q26: Given the project plan shown below, what
Q26: Which of the following is NOT a
Q27: Given the project plan shown below, what
Q28: Spending more money to speed up a
Q32: Which of the following best describes the
Q33: The figure below shows the tasks required