Which of the following statements best describes "crash cost"?
A) Estimated cost to reduce a project task duration by one time unit.
B) Estimated cost to reduce a project duration by one time unit.
C) Estimated cost to reduce the project schedule by one time unit.
D) Actual cost to reduce a project duration by one time unit.
E) Actual cost to change a project schedule.