A Simple Sequential Project (Each Task Must Be Completed Before

Question 3

Multiple Choice

A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: A simple sequential project (each task must be completed before the next one can begin)  has the time estimates (in days)  shown below:   What is the likelihood the project will be completed in 10 days? A) Between 88 and 88 percent B) Between 89 and 92 percent C) Between 93 and 98 percent D) Between 99 and 100 percent What is the likelihood the project will be completed in 10 days?


A) Between 88 and 88 percent
B) Between 89 and 92 percent
C) Between 93 and 98 percent
D) Between 99 and 100 percent

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents