Temby Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours.The company based its predetermined overhead rate for the current year on 10,000 machine-hours,total fixed manufacturing overhead cost of $88,000,and a variable manufacturing overhead rate of $3.20 per machine-hour.Job K418,which was for 50 units of a custom product,was recently completed.The job cost sheet for the job contained the following data:
Required:
a.Calculate the estimated total manufacturing overhead for the year.
b.Calculate the predetermined overhead rate for the year.
c.Calculate the amount of overhead applied to Job K418.
d.Calculate the total job cost for Job K418.
e.Calculate the unit product cost for Job K418.
f.Calculate the selling price for Job K418 if the company marks up its unit product costs by 30%.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q275: Leeds Corporation uses a job-order costing system
Q276: Amason Corporation has two production departments,Forming and
Q277: Franta Corporation uses a job-order costing system
Q278: Saxon Corporation uses a job-order costing system
Q279: Pasko Corporation uses a job-order costing system
Q281: Sullen Corporation uses a predetermined overhead rate
Q282: Job 652 was recently completed.The following data
Q283: Bierce Corporation has two manufacturing departments--Machining and
Q284: Gercak Corporation has two production departments,Forming and
Q285: Bulla Corporation has two production departments,Machining and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents