A revenue variance is unfavorable if the revenue in the static planning budget is less than the revenue in the flexible budget.
Correct Answer:
Verified
Q4: An unfavorable activity variance for revenue indicates
Q5: The main difference between a flexible budget
Q6: Using a flexible budget, actual results can
Q7: A revenue variance is the difference between
Q8: Fixed costs should not be included in
Q10: A favorable spending variance occurs when the
Q11: Differences between the static planning budget and
Q12: When the activity measure is the number
Q13: A revenue variance is favorable if the
Q14: Fixed costs should not be ignored when