Solved

Consider a Project That Has Been Modeled as Follows ADraw the PERT/CPM Network for This Project and Determine Project's

Question 54

Essay

Consider a project that has been modeled as follows:  Activity  Immediate Predecessors  Duration (hr)  A 7 B 10 C  A 4 D  A 30 E  A 7 F  B,C 12 G  B,C 15 H  E,F 11 I  E,F 25 J  E,F 6 K  D, H 21 L  G,J 25\begin{array} { c c c } \text { Activity } & \text { Immediate Predecessors } & \text { Duration (hr) } \\\hline \text { A } & \cdots & 7 \\\text { B } & \cdots & 10 \\\text { C } & \text { A } & 4 \\\text { D } & \text { A } & 30 \\\text { E } & \text { A } & 7 \\\text { F } & \text { B,C } & 12 \\\text { G } & \text { B,C } & 15 \\\text { H } & \text { E,F } & 11 \\\text { I } & \text { E,F } & 25 \\\text { J } & \text { E,F } & 6 \\\text { K } & \text { D, H } & 21 \\\text { L } & \text { G,J } & 25\end{array}
a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path.
b.Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.Can one person perform A, G, and I without delaying the project?
d.By how much can activities G and L be delayed without delaying the entire project?
e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.

Correct Answer:

verifed

Verified

a. blured image Expected Completion Time =...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents