In a ____ relationship,one task cannot finish before another finishes.
A) start-to-start
B) finish-to-start
C) finish-to-finish
D) start-to-finish
Correct Answer:
Verified
Q44: _ results in supporting detail to document
Q45: _ dependencies are inherent in the nature
Q46: _ is the amount of time an
Q47: _ provide(s)a standard format for displaying project
Q48: The _ is a network diagramming technique
Q50: A _ is a hierarchical structure that
Q51: On a network diagram,all arrowheads should face
Q52: The _ for an activity is the
Q53: The ultimate goal of _ is to
Q54: _ is a network diagramming technique used