The ____ is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project.
A) SV
B) CV
C) CPI
D) SPI
Correct Answer:
Verified
Q72: Using good _ can change the false
Q73: The main outputs of the _ process
Q75: The _ is the ratio of earned
Q76: The _ is the ratio of actual
Q77: The main outputs of the _ process
Q78: _ is the earned value minus the
Q79: The _ is an estimate of the
Q80: Using simplified percentage complete amounts for a
Q81: The cost performance index can be used
Q82: _ costs are often much higher for