If a work center has no empty kanban containers,the workers at the work center should do which of the following?
A) Continue to produce as much inventory as they can
B) Produce enough inventory to meet the following day's demand
C) Produce enough inventory to satisfy the master production schedule
D) Stop production
Correct Answer:
Verified
Q3: The ideal setup time for a lean
Q4: Reducing setup time is important because it:
A)Increases
Q5: With regards to suppliers,lean systems typically require:
A)Delivery
Q6: One of the main objectives of a
Q7: The time it takes a container to
Q10: A kanban card is used to signal
Q11: Why is a uniform load desirable in
Q12: Lean thinking can be applied to:
A)Manufacturing
B)Services
C)Functions other
Q13: Reduction of setup time is accomplished by
Q17: If it takes 100 minutes to complete
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents