There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days The standard deviation of the critical path is:
A) 3 days
B) 5 days
C) 9 days
D) 16 days
E) 25 days
Correct Answer:
Verified
Q64: An activity has an optimistic time estimate
Q65: Activity C in a project network has
Q67: The standard deviation of a path is
Q68: The path with the greatest slack is:
A)A-E-H
Q70: The slack for path A-D-H-I is:
A)0
B)3
Q71: There are four activities on the critical
Q84: What is the estimated slack time for
Q86: What is the probability that this project
Q89: What is the estimated standard deviation in
Q96: The expected duration of this project is:
A)13
B)15
C)20
D)52
E)81