In Project Network Analysis,slack Refers to the Difference Between

Question 44

Multiple Choice

In project network analysis,slack refers to the difference between:


A) observed and predicted times
B) optimistic and pessimistic times
C) latest finish and latest start times
D) earliest finish and earliest start times
E) latest start and earliest start times

Correct Answer: