Multiple Choice
Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13?
A) 22.
B) 23.
C) 24.
D) 25.
E) 26.
Correct Answer:
Verified
Related Questions
Q41: In a project network the critical path
Q42: PERT/CPM can answer which of the following
Q43: Given this information about activity H: ES
Q49: A project manager does not need to
Q50: Concerning PERT and CPM:
A)These are two different
Unlock this Answer For Free Now!