Question 60

Multiple Choice

Which statement about a project's IRR is correct? Assume that all projects being considered have normal cash flows and are equally risky.


A) If a project's IRR is equal to its WACC, then, under all reasonable conditions, the project's NPV must be negative.
B) If a project's IRR is equal to its WACC, then, under all reasonable conditions, the project's IRR must be negative.
C) If a project's IRR is equal to its WACC, then, under all reasonable conditions, the project's NPV must be zero.
D) There is no necessary relationship between a project's IRR, its WACC, and its NPV.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents