The controller for Precise Manufacturing has established the following overhead cost pools and cost drivers:
 Budgeted  Overhead Cost Pool  Overhead Cost  Cost Driver  Machine setups $300,000 Number of setups  Material handling 80,000 Units of raw material  Quality control 90,000 Number of  inspection  inspections  Other overhead costs 150,000 Machine hours  Total $620,000\begin{array}{lll}&\text { Budgeted }\\\underline{\text { Overhead Cost Pool }} & \underline{\text { Overhead Cost }} & \underline{\text { Cost Driver }} \\ \text { Machine setups } & \$ 300,000 & \text { Number of setups } \\\text { Material handling } & 80,000 & \text { Units of raw material } \\\text { Quality control } & 90,000 & \text { Number of }\\\text { inspection } && \text { inspections } \\\text { Other overhead costs } & \underline{150,000}& \text { Machine hours } \\\text { Total } &\underline{\$ 620,000} \\\end{array}


 Budgeted Level  Overhead Cost Pool  for Cost Driver  Pool Rate  Machine setups 300 setups $1,400 per setup  Material handling 40,000 units $2.00 per unit  Quality control 800 inspections $60 per inspection  Other overhead 25,000 machine $10 per machine hour  hours \begin{array}{lll}&\text { Budgeted Level }\\\underline {\text { Overhead Cost Pool } }& \underline {\text { for Cost Driver }} & \underline {\text { Pool Rate } }\\\text { Machine setups } & 300 \text { setups } & \$ 1,400 \text { per setup } \\\text { Material handling } & 40,000 \text { units } & \$ 2.00 \text { per unit } \\\text { Quality control } & 800 \text { inspections } & \$ 60 \text { per inspection } \\\text { Other overhead } & 25,000 \text { machine } & \$ 10 \text { per machine hour }\\&\text { hours }\\\end{array}


 Order No. 905 has the following production requirements. \text { Order No. } 905 \text { has the following production requirements. }

 Machine setups: 10 \text { Machine setups: 10 }
 Raw material: 13,400 units \text { Raw material: 13,400 units }
 Inspections: 20 \text { Inspections: 20 }
 Machine hours: 900 \text { Machine hours: 900 } Required:
A. Compute the total overhead that should be assigned to Order No. 905 by using activity-based costing.
B. Suppose that Precise were to use a single, predetermined overhead rate based on machine hours. Compute the rate per hour and the total overhead assigned to Order No. 905.
C. Discuss the merits of an activity-based costing system in comparison with a traditional costing system.

Correct Answer:

verifed

Verified

a.
tends to eliminate the co...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents