Spruce Bank is planning to automate some of its back office functions and reduce operating costs.The installation of new computers and software will require an initial investment of $1,000,000.The savings generated because of reduced personnel cost is $200,000 per year.The bank uses an 8 percent rate of discount to evaluate cost saving projects which are expected to last 10 years.
On further analysis,it is estimated that the project has a finite life of 5 years,i.e.further investment will be required to generate the same savings.Should they undertake the project if they assume a five-year horizon for evaluating the project?
A) Yes,because the NPV of the project is $500,000.
B) Yes,because the NPV of the project is $342,016.
C) No,because the NPV of the project is -$500,000.
D) No,because the NPV of the project is -$201,458.
Correct Answer:
Verified
Q76: As of December 2014, which of the
Q99: Which of the following is NOT a
Q100: As far as regulation is concerned,the increased
Q101: The following information is available on the
Q102: Consider the following two FIs: Company A
Q104: The following information is available on the
Q105: Spruce Bank is planning to automate some
Q106: Consider the following two FIs: Company A
Q107: Spruce Bank is planning to automate some
Q108: Spruce Bank is planning to automate some
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents