A company would most likely have an unfavorable labor rate variance and a favorable labor efficiency variance if
A) the mix of workers used in the production process was more experienced than the normal mix.
B) the mix of workers used in the production process was less experienced than the normal mix.
C) workers from another part of the plant were used due to an extra heavy production schedule.
D) the purchasing agent acquired very high quality material that resulted in less spoilage.
Correct Answer:
Verified
Q76: When multiple labor categories are used,the financial
Q77: The difference between actual and budgeted fixed
Q78: Standards that allow for waste and inefficiency
Q79: Which of the following statements regarding standard
Q80: Standards that are attainable with reasonable effort
Q82: If actual direct labor hours (DLHs)are less
Q83: A bill of material does not include
A)quantity
Q84: Which of the following standards can
Q85: A company wishing to isolate variances at
Q86: The term "standard hours allowed" measures
A)budgeted output
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents