You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.If you crash this project by one day,
What is the total (i.e., direct and indirect) project cost?
A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Correct Answer:
Verified
Q57: A company must perform a maintenance project
Q58: A company must perform a maintenance project
Q59: A simple project listing of five activities,
Q60: You have just been assigned to oversee
Q61: Here are the data for a time-cost
Q63: In CPM analysis, it is generally expected
Q64: Here are the data for a time-cost
Q65: You have just used the network planning
Q66: You have collected the data for a
Q67: You have just performed a CPM analysis
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents