At a Production Level of 4,500 Units,a Project Has Total

Question 78

Multiple Choice

At a production level of 4,500 units,a project has total costs of $107,000.The variable cost per unit is $12.50.Assume the firm can increase production by 1,000 units without increasing its fixed costs.What will the total costs be if 4,800 units are produced?


A) $102,780
B) $104,640
C) $106,400
D) $108,000
E) $110,750