If a project has a net present value equal to zero,then:
A) the total of the cash inflows must equal the initial cost of the project.
B) the project earns a return exactly equal to the discount rate.
C) a decrease in the project's initial cost will cause the project to have a negative NPV.
D) any delay in receiving the projected cash inflows will cause the project to have a positive NPV.
E) the project's PI must be also be equal to zero.
Correct Answer:
Verified
Q6: A project's average net income divided by
Q9: Which one of the following methods determines
Q11: The length of time a firm must
Q12: A project has a net present value
Q15: You are viewing a graph that plots
Q16: Net present value:
A)is the best method of
Q17: Which one of the following methods of
Q18: Which one of the following is a
Q19: Which one of the following will decrease
Q24: If a firm accepts Project A it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents