Which of the following statements is NOT true about finite capacity scheduling (FCS) ?
A) FCS is an extension of Gantt chart methods.
B) FCS requires that jobs be loaded backward from due dates to determine the capacity required at each work center.
C) FCS assumes that jobs are scheduled through a number of work centers, each with one or more machines.
D) In FCS, attention is paid to scarce resources to facilitate job flow and to improve the performance of the shop.
Correct Answer:
Verified
Q8: Scheduling deals with which three conflicting objectives?
A)
Q9: Which of the following is NOT determined
Q10: Shortest processing time (SPT)rule means
A) the job
Q11: Scheduling systems answer all the following questions
Q12: Theory of constraints,as it applies to business
Q14: Critical ratio is
A) the ratio of processing
Q15: In the language of theory of constraints,inventory
Q16: Aggregate planning and scheduling differ in that
A)
Q17: For services,the most common priority dispatch rule
Q18: A bottleneck is
A) a resource that has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents