Which of the following is true for a critical activity?
A) ES = EF
B) EF = LS
C) LF = LS
D) ES = LS
Correct Answer:
Verified
Q8: What is the expected completion time of
Q9: Project management requires
A) scheduling, planning, and controlling.
B)
Q10: The job of the project manager is
Q11: The advantage(s)of the network method over the
Q12: A forward pass of the above network
Q14: Which of the following statements is NOT
Q15: Project managers' work includes
A) planning, scheduling, control,
Q16: Consider the following definitions of slack: #1
Q17: Multiple critical paths can exist under the
Q18: The information calculated from the forward and