When Calculating a Project's Payback Period,cash Flows Are

Question 72

Multiple Choice

When calculating a project's payback period,cash flows are:


A) discounted at the opportunity cost of capital.
B) discounted at the internal rate of return.
C) discounted at the risk-free rate of return.
D) not discounted at all.

Correct Answer: