What happens to the NPV of a two-year project if sales less costs are increased in each year from $1,000 to $1,500? Assume the firm has a 35% tax rate,and a 15% cost of capital.
A) NPV increases by $812.85.
B) NPV increases by $528.36.
C) NPV increases by $500.00.
D) NPV increases by $282.61.