Question 54

Multiple Choice

Which of the following is true of liquidated damages?


A) A small amount is awarded by the court to the plaintiff for a breach of contract which causes no financial injury to the plaintiff.
B) Damages awarded by the court arising from unusual losses, which the parties knew would result from breach of contract.
C) Damages awarded by the court to put the plaintiff in the same position as if the contract had been performed.
D) Damages specified in the contract, where real damages for breach of contract are likely to be uncertain.
E) Courts will enforce these "liquidated" damages to penalize the defendant.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents