The following sequence shows four operations for a computer chip assembly process and the effective capacity of each. Step 1: 500 chips/hour
Step 2: 250 chips/hour
Step 3: 200 chips/hour
Step 4: 550 chips/hour
Suppose the utilization is 70 percent of effective capacity.What is the actual output of the process?
A) 140 chips/hour
B) 350 chips/hour
C) 175 chips/hour
D) 200 chips/hour
Correct Answer:
Verified
Q3: Subcontracting is typically considered at what time
Q4: Process thinking causes managers to address critical
Q5: An example of a short-term capacity increase
Q6: Floor space used to store items to
Q7: Which of the following actions will NOT
Q9: A bottleneck activity in a process is
Q10: Little's Law suggests that the key to
Q11: Under Juran's Law,whenever a problem occurs,what percentage
Q12: The following sequence shows four operations for
Q13: You walk into a hair stylist shop.All
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents