A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below. The customer has offered a $10,000 bonus if the project is completed within 14 days.What is the probability that the bonus will be earned?
A) Approximately 85 percent
B) Approximately 5 percent
C) Approximately 2.3 percent
D) Approximately 97.7 percent
Correct Answer:
Verified
Q5: Task X has a best-case duration of
Q11: An estimate of the duration of a
Q12: A project manager has discovered that three
Q13: Annie is planning a large surprise party
Q15: Annie is planning a large surprise party
Q16: Given the project data below, what is
Q19: A simple sequential project (each task must
Q20: Annie is planning a large surprise party
Q21: If a project path has an expected
Q32: Task X has a most likely duration
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents