The integration of the lowest level of the WBS with the organizational units responsible for performing the work is known as
A) Responsibility matrix.
B) Organization breakdown structure.
C) Work breakdown structure.
D) Priority matrix.
E) Process breakdown structure.
Correct Answer:
Verified
Q29: A "Dissemination Mode" is
A)How project schedules are
Q30: The project scope statement indicates that the
Q31: Having a strong communication plan can go
Q35: A Process Breakdown Structure can provide a
Q37: A Responsibility Matrix will clarify
A)Tasks.
B)Supports.
C)Responsibilities.
D)Both supports and
Q38: The tendency for the project deliverables to
Q39: A key aspect to communication plans are
Q49: The WBS is best suited for projects
Q54: There are 5 steps involved when defining
Q56: If a project is small and does
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents