Tom is responsible for ordering hardware for a custom home his company is building.The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days.Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer.He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days.Tom and the installer share 10 days of
A) Free Slack.
B) Shared Slack.
C) Total Slack.
D) Critical Slack.
E) Functional Slack.
Correct Answer:
Verified
Q22: When creating a project network, your primary
Q23: A project network provides the basis for
Q24: A _ activity is one that has
Q28: The likelihood the original critical path(s)will change
Q29: When completing a backward pass, you carry
Q31: A _ activity is one that has
Q41: If testing cannot be completed any earlier
Q43: System documentation cannot end until three days
Q49: If, for some reason, the project must
Q54: Which of the following is true about
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents