Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?
A) Technical
B) People
C) Equipment
D) Physical
E) Materials
Correct Answer:
Verified
Q6: In reviewing the status of her project
Q7: If resources are not adequate to meet
Q8: Most of the scheduling methods available today
Q9: Susan is to conduct environmental testing but
Q10: All of the following are types of
Q12: A special truck that George needs on
Q13: All resource leveling techniques involve
A)Delaying noncritical activities.
B)Delaying
Q14: Sam, the project engineer, has been scheduled
Q15: Jan is trying to reallocate resources in
Q16: Resource leveling or smoothing can have all
Unlock this Answer For Free Now!