When reducing project duration, the duration for a project that is optimal is at the point where
A) Direct costs are the lowest.
B) Indirect costs are the lowest.
C) Direct costs equal indirect costs.
D) Total project costs are the lowest.
E) The project changes from time-constrained to resource-constrained.
Correct Answer:
Verified