Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333.How is the project doing in terms of schedule?
A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost less than planned
E) There is not enough information to draw a conclusion
Correct Answer:
Verified
Q15: In some cases, conditions or scope can
Q33: A project can have a negative Schedule
Q36: Causes for Scope Creep can include
A)Newly identified
Q37: When reviewing the variance on a project,
Q39: A negative Cost Variance combined with a
Q40: A reason that the duration on a
Q42: The _ rule assumes credit is earned
Q43: Baseline project budgets are derived from time-phasing
Q49: Which of the following methods will measure
Q52: Which of the following methods will measure
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents