When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the
A) 0/100 percent rule.
B) Task complete rule.
C) Degree complete rule.
D) Work complete rule.
E) Percent complete rule.
Correct Answer:
Verified