All of the following describe an appropriate application of Plan Risk Responses in project management EXCEPT:
A) Risk response planning should address both opportunities and threats.
B) Responses should be created for every identified project risk.
C) The expectations of the sponsor and key stakeholders should influence the risk responses that are developed.
D) Often multiple strategies are identified for a single risk.
Correct Answer:
Verified
Q22: Which of the following describes the activities
Q25: Q26: All of the following are among the Q31: All of the following criteria can be Q32: When a project team elects to purchase Q36: Project teams can often identify risks by Q37: Which of the following quantitative risk analysis Q38: Which of the following accurately describes risk Q39: All of the following are benefits that Q43: Identify five common project risk strategies employed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents