Which of the following describes the appropriate use of a cause-and-effect diagram to support project risk analysis?
A) The project team begins by identifying strengths,weaknesses,opportunities and threats.
B) Assumptions and constraints are organized in a fishbone pattern.
C) Although effects are more visible,it is often easier to alter the effect by changing the underlying cause.
D) Team members are encouraged to keep asking "when?" to break down risks into more detailed causes.
Correct Answer:
Verified
Q1: The cost per risk for risks discovered
Q20: Plan Risk Responses is the process of
Q21: On agile projects,detailed risk management activities may
Q27: All of the following describe the appropriate
Q28: Risk response strategies such as mitigation and
Q28: Project managers can identify risks by learning
Q29: All of these describe contemporary methods of
Q29: Risk is often considered in terms of
Q30: All of the following methods have proven
Q34: Which of the following activities illustrates a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents