All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS) for a project EXCEPT:
A) Project teams may adopt a top-down approach to construct the WBS.
B) Project teams may rely upon a WBS from a previous project as a starting point.
C) Project teams may rely upon the project manager to create the entire WBS
D) Project teams may jump start the effort with a brainstorming session.
Correct Answer:
Verified
Q32: Work Breakdown Structures can be displayed in
Q36: The technique for dividing and subdividing the
Q37: On agile projects,the scope definition begins with
Q38: All of the following elements should be
Q40: Which of the following statements concerning work
Q40: For each component in the Work Breakdown
Q41: What are some of the benefits of
Q42: Explain how scope is defined on agile
Q44: Identify and describe the three steps that
Q44: A typical change request form will include
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents