All of the following statements accurately describe a project management plan EXCEPT:
A) It serves as an informal contract between the project team and the sponsor
B) It may be a general,summary document or quite detailed.
C) It may be composed of one or more subsidiary plans.
D) It is developed iteratively,starting at a high level and becoming progressively more detailed as information becomes available.
Correct Answer:
Verified
Q24: A project communications management plan generally includes
Q24: The final item to be recorded on
Q25: Which of the following activities can be
Q27: Several factors can contribute to building relationships
Q29: In the project communications matrix,all of the
Q31: Project managers can encourage open communication by
Q33: Project stakeholders can be prioritized based on
Q36: By identifying stakeholders and their needs,project managers
Q37: Stakeholders include all of the following people
Q40: Communications to stakeholders are necessary for which
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents